We are getting ready to put in a bid as the prime on a federal general construction set-aside. The NAICS code is 236220, Commercial and Institutional Building Construction. We plan to use several subcontractors for different parts of the work. I know there are rules about how much work we have to do ourselves. The solicitation is an IFB, and the bid opening is next month. We have been reviewing the Performance Work Statement, but I have not found a clear statement of the percentage. What are the specific limitations on subcontracting for a federal general construction set-aside, and how is the prime contractor's percentage calculated?
What are the 'limitations on subcontracting' for a federal general construction set-aside?
Ask a question- For a federal general construction set-aside, the prime contractor will not pay more than 85 percent of the amount paid by the Government, excluding the cost of materials, to subcontractors that are not similarly situated entities.
- This rule is found in FAR 52.219-14(e)(3).
- The intent of these limitations on subcontracting is to ensur
1 answer
For a federal general construction set-aside, the prime contractor will not pay more than 85 percent of the amount paid by the Government, excluding the cost of materials, to subcontractors that are not similarly situated entities. This rule is found in FAR 52.219-14(e)(3). The intent of these limitations on subcontracting is to ensure that the small business prime contractor performs a significant portion of the work itself, or uses other similarly situated small businesses. "Similarly situated entity" means a first-tier subcontractor that has the same small business program status as the prime contractor. For example, on an SDVOSB set-aside, an SDVOSB prime can subcontract to another SDVOSB without counting that work against the 85 percent limit. You will need to track the labor and materials costs for each sub to make sure you stay compliant.