What is the difference between an RFI, RFQ, and RFP on SAM.gov?

Ask a question
Asked Active Viewed 19 timesQuestion
1answer

Hey everyone,

I'm new to federal contracting and have been trying to make sense of SAM.gov. I'm looking for grounds maintenance and landscaping contracts, mostly using NAICS 561730.

I keep seeing different types of notices like RFIs, RFQs, and RFPs. For example, I saw a "sources sought notice" for groundskeeping at a VA facility that mentioned an upcoming RFP, but then a small city school district posted an RFQ for school grounds. There was also an RFI about potential new mowing equipment for a federal agency, with a 2-week deadline.

What is the actual difference between an RFI, an RFQ, and an RFP on SAM.gov? How do I know which ones I should respond to with my 9-person crew and which ones are just for information?

asked Jordan P. First-year bidder, landscaping and grounds · Jacksonville, FL · 672 rep

1 answer

0

An RFI is for information, an RFQ is a request for a quote, and an RFP is a request for a proposal.

An RFI is a market research tool. The government does not intend to award a contract from an RFI. Responses to an RFI are not offers and cannot be accepted to form a binding contract. You might see an RFI for potential new mowing equipment, as you described. A sources sought notice is a type of RFI.

An RFQ is used for simpler acquisitions. Agencies use simplified acquisition procedures for purchases up to the simplified acquisition threshold. These procedures are less formal than those for RFPs. An RFQ seeks pricing and a description of the work. Your city school district RFQ is an example of this. State and local government procurements follow their own rules and use their own portals.

An RFP is typically for more complex requirements above the simplified acquisition threshold. This is a formal solicitation. An RFP requires a detailed proposal including technical and price volumes. The Federal Acquisition Regulation (FAR) Part 15 covers contracting by negotiation, which is where RFPs are used. A solicitation expected to exceed $25,000 must be synopsized in SAM.gov. For actions above the simplified acquisition threshold, agencies allow at least a 30-day response time from the date the solicitation is issued.

answered Tom B. Construction estimator, public works · Phoenix, AZ · 906 rep
Thanks, Tom. This clears things up a lot. I'm going to look at the differences between the city school district RFQ and the county's RFP documents for the grounds maintenance bid I'm chasing. · Jordan P. ·

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.