Hey everyone,

I'm trying to figure out the best way to use SAM.gov for finding grounds maintenance contracts, NAICS 561730. I've been seeing a lot of both sources sought notices and Requests for Information (RFI) pop up for federal agencies in my area. I know neither is a direct solicitation, but I'm trying to prioritize my time.

I'm especially interested in small business set-asides, and I've seen some of these notices mention a potential set-aside. Is there a difference in how the government uses a sources sought versus an RFI? Does one type of notice usually lead to a formal solicitation faster or more often than the other? How should my response strategy differ for each one?

asked Jordan P. First-year bidder, landscaping and grounds · Jacksonville, FL · 481 rep

1 answer

0

A sources sought notice is issued to determine if there are enough capable small businesses to set aside a contract, while a Request for Information (RFI) is used to gather general market information when the government does not intend to award a contract (FAR 15.201(e)). The government uses a sources sought notice to test the "Rule of Two" for small business set-asides, seeing if two or more small businesses can do the work at a fair price. If they find enough, the next step is often a formal solicitation. An RFI can be broader, asking about market capabilities, new technologies, or general approaches to a problem. Responses to an RFI are not offers and cannot form a binding contract. I prioritize sources sought notices because they directly inform a potential set-aside. My response strategy for a sources sought is to directly address the capabilities needed for the work, often with a capability statement. For an RFI, I focus on demonstrating our expertise and unique solutions, even if it's more speculative. Neither notice guarantees a solicitation, but the sources sought points to a more immediate need for a specific contract.

answered Marcus T. Verified vendorOwner, janitorial and facilities firm · Columbus, OH · 1227 rep
This is really helpful, Marcus. So for a sources sought, if we respond with a capability statement and they decide to do a small business set-aside, what's the typical next step to actually bid on that contract? · Jordan P. ·

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.