I'm a general contractor, and I'm used to seeing county construction jobs as an Invitation for Bid (IFB) where we submit a lump sum, and then there's a public bid opening. But I just saw the City of Jacksonville issue an RFP for a new fire station, NAICS 236220, with a deadline of July 26. They're asking for qualifications and a fee proposal, not a lump sum. This is new to me for a public construction project. Does an RFP mean they're looking for a design-build or a construction manager at risk approach? How does the city decide who wins with this kind of submittal instead of just picking the lowest bid?
What is an RFP in construction, when every county job I see is a sealed bid with a plan room?
Ask a question2 answers
An RFP in construction can mean the agency is looking for a design-build or construction manager at risk approach, or it can be a qualifications-based selection where price is evaluated separately. Local and state procurements, like the City of Jacksonville's, follow their own state and city procurement codes, not the FAR. The city decides who wins by evaluating the qualifications and the fee proposal according to the criteria outlined in the solicitation's Section M, if they follow a similar structure to federal solicitations. You need to review that section to understand how they will weigh qualifications versus proposed fees. Some jurisdictions will evaluate technical proposals first, short-list the most qualified offerors, and then open the fee proposals only for those short-listed firms. This is different from an Invitation for Bid (IFB), where the lowest responsive, responsible bidder typically wins. I've seen county and school jobs run like this when they want more than just the cheapest option, especially for complex projects or when they want the contractor involved earlier in the design process. It means more work upfront on your proposal, but it can lead to better margins if you're selected.
An RFP for construction means that the City of Jacksonville, like other state and local entities, is using a negotiated procurement approach rather than a sealed bid process. Marcus is right that you need to check the City's specific procurement rules for how they conduct these. Federal agencies use similar methods for certain types of construction, often for design-build, as described in FAR Part 36.3. The city will outline the evaluation criteria, such as experience, past performance, technical approach, and key personnel, in the RFP's instructions to offerors. Your fee proposal will be evaluated based on its reasonableness and how it aligns with your proposed approach, rather than being the sole deciding factor. This type of solicitation requires a more detailed proposal effort than a simple lump-sum bid.