Hey everyone,
I'm bidding on a county grounds maintenance contract, NAICS 561730. It's an IFB, and I downloaded the full package from the county's procurement portal. The original due date was last Friday, but an amendment came out a few days before that. The PDF of the amendment clearly states the new due date is this coming Friday, a full week later. I've been working hard to get my proposal ready for the new date.
However, the main listing on the portal still shows the old due date. Even the email alert I got about the amendment had the old due date in the subject line. My crew is ready, and we have all our equipment lined up, but I don't want to submit on Friday only to have it rejected as late because of a portal glitch. Which date counts here? Who do I even ask about this to make sure my bid isn't tossed out? And is there anything I can do to document this to protect myself?