How is 'cost realism' evaluated in a federal cost-reimbursement contract proposal?

Ask a question
Asked Active Viewed 23 timesAnswered
Short answer · from the accepted reply
  • The contracting officer evaluates cost realism in a cost-reimbursement contract proposal to determine if the proposed costs are realistic for the work proposed, reflect a clear understanding of the requirements, and are consistent with the offeror's technical approach.
  • This process is covered by FAR 15.404-1(d).
  • The government wants to see that your p
Read the accepted answer
1answer

I'm working on a federal Request for Proposal (RFP) for IT services, specifically NAICS 541519, and it's a cost-reimbursement (cost-plus) contract. The due date is in six weeks. My firm has mostly done firm-fixed-price work, so this is a new challenge for us. I'm trying to figure out how the government evaluates 'cost realism' for this type of contract. I've read through Section L and Section M of the solicitation, and they mention cost realism but don't spell out the methodology. What specifically does the contracting officer look for when assessing cost realism in a proposal for a cost-reimbursement contract?

asked Priya S. Verified vendorCapture manager, IT services · Herndon, VA · 1127 rep

1 answer

2
Accepted answer

The contracting officer evaluates cost realism in a cost-reimbursement contract proposal to determine if the proposed costs are realistic for the work proposed, reflect a clear understanding of the requirements, and are consistent with the offeror's technical approach. This process is covered by FAR 15.404-1(d). The government wants to see that your proposed costs are reasonable, allowable, and allocable based on your proposed technical solution.

They will often compare your proposed costs to independent government estimates, past contract performance data, and other proposals received for the same requirement. Expect them to scrutinize direct labor rates, indirect rates, and material costs to ensure they align with your company's accounting practices and the work described in your technical volume. If your proposed costs seem too low to realistically accomplish the work, the contracting officer might adjust them upward for evaluation purposes, which could impact your competitive standing, even though you will only be reimbursed for actual, allowable costs incurred.

answered Jo R. Freelance proposal writer · Denver, CO · 1390 rep
This is why I mostly stick to firm-fixed-price contracts. Cost-reimbursement contracts just add too many layers of scrutiny and potential for the government to mess with your pricing, even if it's just for evaluation. · Marcus T. ·