What is the process for requesting a 'preaward debriefing' if my offer was excluded from the competitive range?

Ask a question
Asked Active Viewed 20 timesAnswered
Short answer · from the accepted reply
  • You request a preaward debriefing by submitting a written request to the contracting officer within 3 days after receiving the notice of exclusion from the competitive range, according to FAR 15.505(a).
  • The notice you received about your exclusion should have identified the contracting officer.
  • You can send your written request to that individual.
Read the accepted answer
1answer

My company received a notice that our proposal for a federal IT services contract, NAICS 541519, was excluded from the competitive range. It was a small business set-aside. I have heard about something called a "preaward debriefing" and I am trying to figure out how to request one. The notice did not include instructions for a debriefing, and I want to make sure I follow the correct process. I know there are deadlines for these things. Where do I go to officially request a preaward debriefing, and what information do I need to include in that request?

asked Priya S. Verified vendorCapture manager, IT services · Herndon, VA · 1127 rep

1 answer

1
Accepted answer

You request a preaward debriefing by submitting a written request to the contracting officer within 3 days after receiving the notice of exclusion from the competitive range, according to FAR 15.505(a). The notice you received about your exclusion should have identified the contracting officer. You can send your written request to that individual. The FAR does not specify a required format for the request, but it is good practice to include the solicitation number, your company's name and Unique Entity ID (UEI), and a clear statement that you are requesting a preaward debriefing.

For state and local contracts, the process and deadlines for requesting a preaward debriefing, if available, will be outlined in the specific solicitation documents or the state or local procurement code. Always check the solicitation and any vendor guides on the relevant state procurement portal for those instructions.

answered Jo R. Freelance proposal writer · Denver, CO · 1390 rep
Jo R. is correct. The contracting officer is not required to provide a preaward debriefing if the exclusion was based on a non-responsibility determination, but they may do so at their discretion. · Dana K. ·

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.