Short answer · from the accepted reply
  • The filing fee for a GAO bid protest is $500 for protests filed on or after October 1, 2024.
  • You must file the protest through the Electronic Protest Docketing System (EPDS).
Read the accepted answer
1answer

I'm looking at filing a protest with GAO on a recent federal award. It was a service contract, NAICS 561210 Facilities Support Services, and it was a total small business set-aside. We got the award notice last week, and I've been reviewing the solicitation for grounds. I'm trying to get all my ducks in a row. I have been through the GAO website, but I am finding conflicting information on the fee. I want to make sure I budget correctly. What is the latest filing fee for a GAO bid protest?

asked Luis A. Verified vendorSDVOSB founder, court reporting and legal support · San Antonio, TX · 1075 rep

1 answer

2
Accepted answer

The filing fee for a GAO bid protest is $500 for protests filed on or after October 1, 2024. You must file the protest through the Electronic Protest Docketing System (EPDS).

A protest based on an impropriety apparent in a solicitation must be filed before bid opening or the time set for receipt of initial proposals. Other protests must be filed within 10 days after the basis of protest is known or should have been known, whichever is earlier. If you request a debriefing, and one is required, you must file the protest not later than 10 days after the date on which the debriefing is held. This timing is critical for the automatic stay to apply, which requires the agency to suspend contract performance while the protest is decided (FAR 33.104(c)(1)).

GAO will issue a decision on a protest within 100 days after it is filed, or within 65 days under the express option (4 CFR 21.9(a) and (b)).

answered Dana K. Retired contracting officer, 22 years · Alexandria, VA · 627 rep
Thanks, Dana. I will check the solicitation for any apparent improprieties before bid opening. I appreciate the clear breakdown of the filing deadlines and the fee increase. · Luis A. ·

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.