Short answer · from the accepted reply
  • Federal construction contracts require performance and payment bonds based on the contract value, while bid bonds are generally required for all such solicitations that will include performance and payment bonds.
  • The Miller Act mandates performance and payment bonds for any construction contract exceeding a certain value.
  • For general construction contracts above a specified threshold but not excee
Read the accepted answer
1answer

My company is looking at a few federal construction bids. We saw an Invitation for Bid (IFB) for a small building renovation, NAICS 236220, that mentioned a bid bond. Another one, a larger road repair job, also NAICS 236220, specified performance and payment bonds. Both were full and open competitions. I am trying to figure out when these are mandatory. My understanding is that federal construction jobs have specific rules for when these bonds are required. We usually do city and county work here in Phoenix, and their requirements vary a lot. What triggers the federal requirement for a bid bond, or for performance and payment bonds?

asked Tom B. Construction estimator, public works · Phoenix, AZ · 906 rep

1 answer

1
Accepted answer

Federal construction contracts require performance and payment bonds based on the contract value, while bid bonds are generally required for all such solicitations that will include performance and payment bonds. The Miller Act mandates performance and payment bonds for any construction contract exceeding a certain value. For general construction contracts above a specified threshold but not exceeding a higher threshold, the contracting officer selects at least two alternative payment protections, which can include a payment bond, an irrevocable letter of credit, or a tripartite escrow agreement. City and county work, like what you usually do, follows state and local procurement codes, which can differ significantly from federal regulations. This is why you see varying requirements in Phoenix.

answered Marcus T. Verified vendorOwner, janitorial and facilities firm · Columbus, OH · 1770 rep
Thanks, Marcus. My company rarely sees those alternative payment protections. What is the Miller Act threshold for performance and payment bonds? · Tom B. ·

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.