  • DCAA commonly identifies issues with internal controls and proper cost accounting during audits of federal contractors.
  • They focus on whether a contractor's accounting system can track costs by contract line item and if the costs are allowable, allocable, and reasonable.
  • Common findings include inadequate timekeeping systems, inconsistent application of indirect cost rates, unallowable costs charg
Read the accepted answer
1answer

My company, an IT services firm (NAICS 541519), is preparing for a potential DCAA audit. We are a prime contractor on a federal time-and-materials contract for network operations, and the contracting officer mentioned we might be subject to an audit soon. We have our policies and procedures documented for things like timekeeping and expenses, but I am looking for insight beyond that. We have read through the DCAA contract audit manual, but I want to know what common issues DCAA identifies during audits of federal contractors. What areas do they typically focus on, and what are the most frequent findings they cite?

asked Priya S. Verified vendorCapture manager, IT services · Herndon, VA · 1127 rep

1 answer

4
Accepted answer

DCAA commonly identifies issues with internal controls and proper cost accounting during audits of federal contractors. They focus on whether a contractor's accounting system can track costs by contract line item and if the costs are allowable, allocable, and reasonable. Common findings include inadequate timekeeping systems, inconsistent application of indirect cost rates, unallowable costs charged to the government, and insufficient documentation to support incurred costs.

For a time-and-materials (T&M) contract, DCAA will examine how direct labor hours are tracked and billed at the fixed hourly rates. They also review the actual costs for materials. The Federal Acquisition Regulation (FAR) Part 31, Contract Cost Principles and Procedures, defines what costs are allowable. DCAA looks for compliance with these principles. My company sees many small shops get tripped up on charging unallowable costs like marketing expenses or executive bonuses to government contracts. They also check that employees are charging their time correctly to the right projects, especially for T&M contracts.

answered Tom B. Construction estimator, public works · Phoenix, AZ · 906 rep