What actions can an agency take if a 'bid protest' is filed to GAO, especially regarding an automatic stay?

Ask a question
Asked Active Viewed 16 timesAnswered
Short answer · from the accepted reply
  • When a bid protest is filed with GAO and triggers an automatic stay, the agency generally must suspend performance of the awarded contract, but the head of the contracting activity can make a written finding to override this.
  • The automatic stay applies when the agency receives GAO notice of a protest within 10 days after contract award or within 5 days after a debriefing date offered for a require
Read the accepted answer
1answer

We were notified of an award on a federal services contract, NAICS 541611, within the simplified acquisition threshold. We lost the bid, and the award notice went out. The prime on our team filed a protest with GAO yesterday, within the 10 days after contract award. I know about the automatic stay, but I am trying to understand what the agency can do in response to it. Can the contracting officer just ignore it, or does the agency have options to continue with the award? What actions can an agency take if a bid protest is filed to GAO, especially regarding an automatic stay?

asked Dana K. Retired contracting officer, 22 years · Alexandria, VA · 627 rep

1 answer

3
Accepted answer

When a bid protest is filed with GAO and triggers an automatic stay, the agency generally must suspend performance of the awarded contract, but the head of the contracting activity can make a written finding to override this. The automatic stay applies when the agency receives GAO notice of a protest within 10 days after contract award or within 5 days after a debriefing date offered for a required debriefing, whichever is later. The contracting officer must then suspend performance or terminate the awarded contract unless the head of the contracting activity makes a written determination that contract performance is in the Government's best interests or that urgent and compelling circumstances significantly affect the interests of the United States (FAR 33.104(c)(1) and (2)). For state and local procurements, the specific actions an agency can take depend on the relevant state procurement code and the portal's vendor guide, as these rules vary by jurisdiction.

answered Jo R. Freelance proposal writer · Denver, CO · 1390 rep
That's a good summary. The automatic stay is a big deal for us as small businesses. It means the government takes the protest seriously and has to pause work while GAO reviews it. · Luis A. ·

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.