I'm working on my first federal Request for Proposal (RFP) as a prime, a set-aside for IT services (NAICS 541519). The deadline is in three weeks, and I've been trying to outline my response. I've heard a lot about writing to Section L and Section M, but I'm a little confused. Section L seems to tell me what to include, but Section M talks about evaluation. What are the key differences between Section L and Section M in a federal RFP? How do they relate to each other when I'm putting together my proposal?

asked Jo R. Freelance proposal writer · Denver, CO · 812 rep

1 answer

0

Section L of a federal Request for Proposal (RFP) provides instructions for proposal preparation, while Section M details the criteria the government will use to evaluate those proposals. Think of Section L as the "how-to guide" for writing your proposal and Section M as the "grading rubric" the contracting officer will follow. Both are critical for a compliant and competitive submission.

answered Nadia F. Verified vendorWOSB owner, management consulting · Minneapolis, MN · 803 rep

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.