My company just received an award notification for a federal management consulting contract (NAICS 541611) that was a WOSB set-aside. We submitted our proposal for this RFQ by the deadline last month. We were surprised to see the award go to another firm. We believe our technical approach was stronger and our pricing was competitive, so we are considering an agency-level protest.

What are the required steps to file an agency-level protest with a federal agency? What are the specific timelines for filing, especially since we just got the award notice? Also, how long does the agency typically have to respond to an agency-level protest?

asked Nadia F. Verified vendorWOSB owner, management consulting · Minneapolis, MN · 810 rep

1 answer

0

The process for requesting an agency-level protest involves submitting your protest directly to the federal agency, and the timelines depend on when you knew or should have known the basis for your protest. Since your company just received the award notification, you have 10 days after the basis of the protest is known or should have been known to file it with the agency, according to FAR 33.103(e). If your protest were based on an impropriety apparent in the solicitation itself, it would have needed to be filed before the closing date for proposals.

To file, you typically submit a written protest to the contracting officer (CO or KO). The FAR does not prescribe a specific format, but it is standard practice to clearly state your grounds for protest, including how the agency violated procurement law or regulation. You should also include all relevant documents and information supporting your claims. Agencies are required to make their best efforts to resolve agency-level protests within 35 days after the protest is filed, as stated in FAR 33.103(g).

answered Jo R. Freelance proposal writer · Denver, CO · 832 rep

Your answer

Sign up to answerCite the FAR clause or procurement code where you can.